QUEST 100 % inspection of output is: 
A the best proven method to ensure quality 
B is expensive, ineffective approach to quality management 
C can never be, justified 
D can still leave some defects undetected 
E B and D only 
參考答案:E
QUEST Quality control charts show a characteristic of the product or service against: 
A the specification limits 
B customer requirements 
C control limits based on three standard deviations in each direction 
D control limits based on six standard deviations in each direction 
E A and D only 
參考答案:C
QUEST Variables quality data are: 
A quantitative or qualitative data 
B quality data for which the product or service is designed and built 
C reflect measurements on a continuous scale of a characteristic of the produce or service. 
D Indicate management's understanding of the concept of variability 
E B and C only 
參考答案:E
QUEST Attributes quality data are: 
A quantitative or qualitative data 
B quality data for which the products or services is designed and built. 
C reflect measurements on a continuous scale of a characteristic of the product or service 
D indicate management's understanding of the concept of variability 
E A and B only 
參考答案:E

QUEST Which of the following are among Phil Crosby's "absolutes of quality'. 
A the performance of standard is zero defects 
B do everything right the first time, each time 
C constantly improve each product and each service 
D the measurement system is the cost of nonconformance 
E A and D only 
參考答案:E