2010年PMP美國項目管理考試習題及答案六
QUEST The scope of a project can be expected to change if:
A The project manager must provide cost estimates without having a design concept
B Oversimplification (underestimating) of the nature of the work occurs
C The project manager is assigned after the project is defined, and the cost and schedule are approved
D A clear objective is not provided
E All of the above are possible based upon the situation
參考答案:E
QUEST The most common non-behavioral reason for projects being completed behind schedule and over budget is:
A Selecting the wrong person as the project manager
B Selecting the wrong person as the sponsor
C Accepting a high-risk project
D Ill-defined requirements
E All of the above
參考答案:D
QUEST The appointment or selection of a project sponsor is often based upon:
A The strategic importance of the project
B Who the customer is
C Whether the organization is project or non-project-driven
D The profitability of the project
E All of the above
參考答案:E
QUEST The "rolling wave" or "moving window" concept is used most frequently on projects where:
A The baseline is frozen for the duration of the project and no scope changes are permitted
B Marketing is unsure of what the customer actually wants and reserves the right to make major scope changes
C The low levels of the work breakdown structure are known with certainty for the next three to six months, but the remaining tasks are based upon the results of the first three to six months of work
D Networking techniques are not appropriate
E All of the above
參考答案:C
QUEST Interfacing with the customer after project go-ahead is the responsibility of:
A Project sponsor
B Project team
C Project manager
D Functional manager
E All of the above are possible, based upon the size and complexity of the project
參考答案:C
試題推薦:
2010年PMP美國項目管理考試習題及答案一
2010年PMP美國項目管理考試習題及答案二
2010年PMP美國項目管理考試習題及答案三
2010年PMP美國項目管理考試習題及答案四
2010年PMP美國項目管理考試習題及答案五
2010年PMP美國項目管理認定考試全真模擬試題精選1
2010年PMP美國項目管理認定考試全真模擬試題精選2
2010年PMP美國項目管理認定考試全真模擬試題精選3
- 1使用混凝土輸送泵應注意十二點
- 2太中銀鐵路某隧道出進口段施工組織設計
- 3二級建造師薪資
- 42015年陜西省安全工程師報名時間為4月8日-29日
- 52015年咨詢工程師《工程項目組織與管理》每日一練8.21
- 62015年注冊監(jiān)理工程師《理論法規(guī)》習題(15)
- 72010年PMP美國項目管理考試習題及答案28
- 82015二建備考中看過的知識點記不住怎么辦
- 9武漢CBD第64層建設如火如荼進行中 預計明年春節(jié)前封頂
- 102015年咨詢工程師每日一練免費在線測試(2015.6.8)
- 112015招標師專業(yè)實務考點:工程質量的兩個控制環(huán)節(jié)
- 12二級建造師法規(guī)知識點:建設工程合同
- 132015年安全工程師《生產管理知識》典型題(9)
- 14下列監(jiān)理工作措施中,屬于進度控制技術措施的是
- 152015安全工程師《生產法及相關法規(guī)》提分試題(6)
- 16《工程咨詢概論》知識點:工程咨詢業(yè)的特點
- 172015年安全工程師相關法律知識練習(9)
- 18某電視中心工程施工進度總計劃
- 192015年安全工程師考試《事故案例分析》模擬題(9)
- 20什么是地震中的地聲現象
- 21受波浪沖擊駁岸植物生態(tài)護坡技術研究
- 222015年招標師考試習題精選:資格預審文件的基本內容
- 23內蒙古某隧道出口施工組織設計
- 243年建造師考試坎坷路帶給您啟示
- 25我國將從六方面發(fā)展智能交通
- 262015年招標師案例分析詳解(2)
- 272012年一級建造師《項目管理》:施工成本控制之三
- 28首鋼與中聯重科簽署戰(zhàn)略合作協議
- 29PMP如何填寫資格審核表
- 302015年造價員基礎知識:電力電纜的分類
成都公司:成都市成華區(qū)建設南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務大廈18樓